3.
Natural Gas Distribution
-
-
Section 2 -
The under progress & new
Projects
-
1.
Administration buildings
-
2.
Electricity Generation
-
3.
Electricity Distribution &
Transmission
-
4.
Natural Gas Distribution
-
5.
Water Distribution &
Production
Section 1 - The Accomplished
Projects during 2005
Power
Generation
Layyah Power Station:
Completion of Nano-Filtration
system for the Desalination Unit
No. 9.
Amendment of control &
maintenance systems of four
desalination units (No.5 and 6).
Some amendments & related civil
works were carried out as
follows:
-
-
Construction of new 40 MW
boilers.
-
-
132 KV switchgear
-
-
Control Cameras.
Wasit Power Station:
Completion of Phase 5 Wasit
Power Station Project,
Installation and commissioning
the tenth and the eleventh units
of 2x100 MW Frame 9 Gas Turbine.
The new two units was
commissioned on 20th, June and
24th, October 2005, including
Civil works of the two new gas
turbines.
Khorfakkan Power Station:
Amendment of control &
maintenance systems of gas
turbines No (1&2).
Kalba Power Station:
Amendment of control &
maintenance systems of gas
turbine No 1.
Expansion of compound wall to
cover the additional land of the
Station.
Main Office:
Constructing building of "SIT
Ladies Division"
Accomplishment of Geographical
Information System.
Transmission &
Distribution Substations and
Networks:
132 KV Transmission
Substations.
-
Installation of Majaz-4
Substation (225 capacities)
at Sharjah city, it
consists of 3
transformers with 75 MVA
capacities each.
-
Development of Layyah & Sports
Center 132 KV substations.
-
33KV distribution substations.
-
Installation & commissioning
of three substations (two in
Sharjah city at Al Qassimiya
& Abu Shagara-4 areas, and
one in Khorfakkan).
11/6.6
KV distribution substations
Addition of 348 substations
comprising of 393 transformers
having capacity of "391.4" MVA
(out of which 318 substations
are located in Sharjah city
comprising of 347 transformers
of 338.1 MVA, 18 "11KV"
substations comprising of 25
transformers of 29.1 MVA in
Khorfakkan and 12 "11KV"
substations comprising of
21transformers of 24.2 MVA in
Kalba).
Electricity Distribution
Networks
132 KV Underground Cables:
13 km were laid in Sharjah
city.
33 KV Underground Cables:
50 km were laid in Sharjah city.
(11&6.6) KV Underground Cables
150.50 km were laid (out of
which 134.83 km in Sharjah city,
5.73 km in Khorfakkan and 9.94
km in Kalba).
Street lighting
Lighting of Sharjah Ring
Road, some residential areas (
Jazaat and Falaj), sports Clubs
(playgrounds of football,
Basketball and volleyball),
parks (at Nahda, Azra, Shahba
and Gurain), some bridges and
lagoons of Kalba.
Fire fighting system
Accomplishment of fire fighting
systems in Khorfakkan.
Other constructions
Transmission and Construction of
four supplementary feeders from
industrial area-17, to
industrial area-7 and sport
center area (two for each).
Construction of "shunt reactor
banks" at industrial area-7.
Construction of emergency office
and garage in Khorfakkan.
Construction of workshop of
maintenance & checkup meters in
Khorfakkan.
Construction of a boundary wall
to cover the additional land of
Kalba Power Station.
Natural Gas Distribution
Using of Natural Gas as fuel
for vehicles:
The 1st Phase of this project
- which aim to apply the use of
the most efficient, cleanest and
safest fuel energy sources to
safeguard the environment &
public health and safety of the
society - was completed. It
covers the conversion of 300
vehicles of SEWA to use the
Compressed Natural Gas as fuel
instead of petrol.
His Highness Sheikh Sultan bin
Mohammed bin Sultan Al Qassimi,
the Crown Prince, Deputy Ruler
of Sharjah and Chairman of SEWA
Board of Directors opened the
first Station of Compressed
Natural Gas Filling for vehicles
-the first of its kind in UAE
and the Arabian Gulf Countries
Region- at Halwan area on
Saturday, 12 February, 2005.
As part of the efforts towards
achieving the ideal use of
Sharjah natural gas distribution
network and in line with efforts
made to utilize the natural gas
as a future strategic fuel
source as well as preserve the
environment, SEWA signed a
contract with Adnoc Distribution
to construct four CNG filling
stations during 2006 followed by
More CNG filling Stations in
order to meet the needs of
vehicles and cars owned by
Sharjah government departments
and authorities including
Sharjah transport, while the
taxi cars as well as cars owned
by private organizations and
individuals will be covered
latter.
Gas Supply to remaining
residential areas.
New gas installations were made
to supply gas to the commercial
and industrial areas (Al Nahda,
Al Khan and Al Mamzar).
Water Production &
Distribution:
Desalination plant and
units:
Unit No. 8 in Layyah
Desalination Plant has been
upgraded and refurbished.
New Well fields and boreholes.
Wadi Sa'adiah Well field
This well field is located
halfway between Tawi Mohafiz
and Tawi Nazwa. It was
commissioned in June, 28th 2005.
It consists of “28” produced
wells with 4.2 million gallon
per day available capacity.
Tawi Wahoosh Well field
This Well field was
commissioned in August, 10th
2005. It consists of “29”
produced wells with 4.4 mg per
day available capacity. It is
proposed to increase its
production from 3 to 5 mgd by
drilling 20 additional
boreholes.
New drilled boreholes
Five new boreholes are drilled at
Seih harmal Well field to
augment its yield to 2.25 mgd.
Water Transmission &
Distribution
Water Distribution
Networks
Laying of various diameters
Water pipelines & mains of
162.65 km, out of which 120.25
km in Sharjah city, 6.03 km in
Khorfakkan and 36.38 km in Kalba).
New
Connections:
(2650) additional Connections
were carried, 2143 in Sharjah
city ( 947 residential sector,
821 commercial sector and 375
industrial sector), 283 in
Khorfakkan (247 residential
sector and 36 commercial sector)
and 224 in Kalba (180
residential sector, 22
commercial sector and 22
industrial sector).
Load
Dispatch Center (LDC)
Works were done by the
Contractor (Areva T&D company):
Completing technical works
relating to adaptation and
control of power stations and
distribution & transmission
substations up to 33 KV.
Completing the computer system
of adaptation and control of
power stations and distribution
& transmission substations
completing the Fiber-optic
network
Works were done by the LDC:
- completing recruitment of
Center's staff for the various
technical section.
- Laying the Fiber-Optic cables
to the stations and new
buildings of SEWA.
- Updating entering the new
distribution & transmission
substations.
-
Considering a coordination
mechanism between the Center
and Layyah & Wasit stations and
the Directorate of Transmission
& Distribution.
completing the design works of
the new information network of
SEWA which will link all SEWA's
stations, directorates and
departments In Sharjah by using
Fiber-Optic cable Network
Top
Section 2 - The under
progress & new Projects
Pursuant to the directives made
by His Highness Sheikh Dr.
Sultan bin Mohammed Al Qassimi,
member of Supreme Council and
Ruler of Sharjah who devotes
continuous attention and
unlimited support to the
modernization projects
especially those concerned with
infrastructure to enhance the
development in various fields
and in response to his concern
to ensure the best modern living
standards for both nationals and
residents. H.H Sheikh Sultan
bin Mohammed Bin Sultan Al
Qassimi, the Crown Prince,
Deputy Ruler of Sharjah and the
Chairman of SEWA’s Board of
Directors endorsed the 2006
budget of SEWA amounting to Dhs
3,394,000,000. The budget
allocates an amount of Dhs
1,552,172,000 for operating
expenses, running expenses and
the semi capital expenses while
Dhs 1,841,828,000 is allocated
for the new projects. Following
are some of these projects:
Administration buildings:
Construction of new building for
Qasimiyah Branch Office is
accomplished. Shifting to the
new building took place in May
2006.
Extension to the Head Office will be
constructed with AED 5 million
cost
Electricity Generation:
Establishment of Hamriyah
Station for Elec. Generation &
Water Desalination:
Work was started to develop this
new power in Hamriyah town. The
first phase of the project
comprised of four Frame 9 gas
turbines of 100 MW capacity
each. The first and second
phases of gas turbines
commissioned in June and July
2006 respectively while the
third and fourth gas turbines
will be commissioned in
December 2006 and February 2007
respectively.
The total cost of the Phase 1 is
AED 965 million, out of which
AED 650 million for supply,
installation and commissioning
of four gas turbines and 2
emergency generators of 100 MW
capacity each, AED 45.5 million
for the civil works relating to
the new turbines, AED 65 million
for the civil works relating to
the new station, AED 84 million
for supply, installation and
commissioning of switchgears and
equipment of 220/132 KV
Substation, AED 55 million for
land reclamation works of Phase
1 , AED 50 million for 132 KV
transmission substation and
33KV Distribution Substation
including the civil works, AED 9
million for construction of 2
fuel tanks and 2 firefighting
tanks, AED 8 million for
construction of the compound
wall, AED 6 million for
construction of the
administration building, stores
and workshops, AED 1.5 million
for two supply of cranes for the
new station
Wasit Power Station:
Phase 6 of Wasit Power Station
Project, comprises of two Rolls
Royce Aero Derivative Gas
Turbines of 50 MW capacity each
will be commenced. Both units
are scheduled to be commissioned
by 2007 with total cost of AED
155 million.
Layyah Power Station:
Amendment of conrol &
maintenance systems of Units
Nos. 7 & 8 with total cost of 15
million
Additional works including civil
works with total cost of 5.2
million as follows:
-
-
Replacement of old air
compressors with total cost of 3
million
-
-
Installation of protection
equipment for G. T Nos. A & B
-
-
Construction fo administration
building with total cost of 3.2
million
Khorfakkan Power Station
Automatic cleaning filters will
be provided with cost of AED 4
million
Additional compound wall will be
constructed with AED 1 million
cost
Construction of Stores access
roads in the station (Interlock)
with a cost of one million
dirham.
Three new generators:
Three new generators will be
supplied with cost of AED 93000.
The first generator of 1000 KW
capacity for Abu Mussa Power
Station, the second one of 500
KW capacity for Mohazeb Pumping
Station, while the third one 120
KW capacity for Nassiryah
Emergency station.
Electricity Distribution & Transmission
220 & 132 KV electrical
transmission substations:
Construction of 220 KV electrical
transmission substation at Tai
area in Sharjah comprising of
2x100 MVA transformers with
total cost of AED 236 Million
including cabling cost. The
substation is scheduled to be
commissioned by 2007
Construction of 132 KV electrical
transmission substation at Abu
Shaghara area in Sharjah
comprising of 3x100 MVA
transformers with total cost of
AED 50 Million. The substation
is scheduled to be commissioned
in 2006
3/A/3: Construction of 5 additional
feeders with total cost of AED
15 million, out of which 3
feeders for Hamriyah 132 KV
Substation, one for Industrial
Area 17 132 KV Substation and
one for Sport Center 132 KV
Substation
33 KV Distribution Substations:
Construction of six 33 KV Distribution
Substations with total cost of
AED 60 million (including cables
and capacities) in Sharjah City
(areas of Majurah, Al Nahda, Al
Ramtha, Al Ramlah, Mohweleh
Commercial, Expo and Al Mamzr2 )
Enhancements of the following
substations with total cost of
AED 3 million: Industrial 7B,
Industrial15, Industrial 17A,
University 3, Saja'a, Falah,
Water, Qassimyah 1 and Majaz.
Electrical transmission &
Distribution Networks:
Construction of 172.5 Km of 132 KV
cables with total cost of AED 96
million as follows: (72 km for
area of the schools, 36 km
from Hamriyah Power Station to
Hamriyah Transmission
Substation, 36 km for Mamzar
Substation and 28.5 km from
Industrial 17 to Sport Center.
Upgrading of 24 km of Hamriyah – Saja's
Cable from 123 KV to 220 KV with
total cost of AED 18 million.
Construction of 126 km of 33 KV cables
in Sharjah city with total cost
of AED 17 million as follows: 86
km of 630 mm dia cables, 28.6 km
of 400 mm dia. And 11.4 km of
400 mm dia. single cables to
reinforce the network.
construction of new substations with
AED 4 million to connect
electrical supply to the new
low-cost houses at areas of
Qadisiyah, Luluyah, Jaradia and
Zibara in Khorfakkan
Extension of the Electrical Distribution
Network in Kalba with total cost
of AED 4 million
Street Lighting:
Street lighting projects with total cost
of AED 30.8 million are executed
in 2006 ( out of which AED 30
million for Sharjah city, AED
800,000 for Khorfakkan and
Kalba.
Fire Fighting Systems:
New fire fighting systems with total
cost of AED 3.6 million will be
provided in 2006 (out of which
AED 3.2 million for ten 33 KV
distribution substations in
Sharjah City and AED 0.4 million
the Stores, Head office and
Workshop in Khorfakkan.)
Other new transmission and
Distribution Projects:
New 2X 50 MVA, 220/33 KV transformers
and 33 KV Switchgear will added
to the 220 KV Wasit Transmission
substation with total cost of
AED 22.32 Million including the
civil works
A new administration building for the
Directorate pf Transmission &
Distribution is to be
constructed with total cost of
AED 4.5 million including cost
of A/C systems and other
facilities. Addition of 15 new
capacitors with total cost of
AED 4 million (including civil
works). Supply of new generator
of 500 KW capacity for Nahwa
Substation in Khorfakkan with
total cost of AED 0.5 million.
Construction of the compound
wall and interlocks for Nahwa
Substation and interlocks for
Khorfakkan Station with total
cost of AED 0.675
million.Building of new stores
in Kalba with total cost of AED
1.1 million (including
backfilling and leveling works)
Natural Gas Distribution
Use of CNG as Fuel for Vehicles:
Phase 2 of this pioneering and
vital project reflecting the
commitment of SEWA to
maintenance of environment and
public health, will be started
soon. Phase 2 of the CNG driven
vehicles project will cover the
conversion of vehicles and cars
belong to the local government
departments and authorities of
Sharjah such Sharjah as well as
taxis and vehicles and cars
belong to the individuals and
private companies to use natural
gas as fuel instead of petrol. A
number of vehicles gas filling
stations will be established in
Sharjah to supply such vehicles
and cars with natural gas. The
project will promote the image
of SEWA as an environment
friendly organization and
enhance the efforts made seek
for cleanest renewable fuel
resources and ensure the
rational use of this strategic
energy resource to protect the
environment
Other projects of Natural Gas:
-
-
Construction of a new
administration
building for the
Directorate of
Natural Gas
Distribution. With
total cost of AED 4
million (including
interlocks/ compound
wall/workshop). The
building is
scheduling to be
completed by the 2nd
half of 2006.
-
-
Construction of new standby
storage tank of
natural gas, with
AED 3 million cost
in progress
-
-
Feasibility study with cost of
AED 0.5 million on
project of Natural
gas cooling systems
for buildings
-
-
Connection of gas
supply the
residential areas:
-
Work is in progress to connect
piped natural gas
supply to the
remaining
residential,
commercial and
industrial building
in Sharjah city with
total cost of AED 10
million
-
Water Distribution & Production:
Water Desalination Plants:
Wasit Desalination Plant:
It is planned to supply, install
and commission ten MED
desalination units of 8 million
gallons per day capacity each
(80 mgd total capacity) during
2007 and 2008 with total cost of
AED 900 million. Including
distribution pipelines.
Layyah Desalination Plant:
MED Desalination unit with
capacity of million gallons per
day and R.O desalination unit of
5 million gallons per day will
be commissioned at Layyah Power
Station by 2007 with total cost
of AED 300 million including the
civil works, 4 boilers,
reclamation and sea backing
filling works.
Khorfakkan Desalination Plant:
R.O Desalination Unit of
capacity of 5 million gallons
per day and with total cost of
AED 90 million will commissioned
in Khorfakkan by Summer 2007.
Kalba Desalination Plant:
R.O Desalination Unit of
capacity of 2 million gallons
per day commissioned in Kalba in
June 2006 with total cost of AED
50 million including sea water
pumping house.
Two underground water storage
tanks of capacity of 3 million
gallons per day each and with
total cost of AED 8 million
will be completed and
commissioned by 2007
Compound wall, office building
and additional lab will
constructed at Khorfakkan Power
Station with total cost of AED
0.5 million
New wellfields:
Projects of developing new water
wells with total cost of AED 3.5
million are under progress out
of which AED 2 million for
additional works at Al Wohoosh
Wellfield and AED 1.5 million
for drilling new wells in
Sharjah, Khorfakkan and Kalba.
Aquifer
Storage & Recovery project:
The execution of Phase 2 of this
project, with total cost of AED
5 million, is under progress
Halwan Water Storage Tank
Halwan Water Storage Tank of 15
million gallons capacity and
with total cost of AED 30
million will constructed and
completed by Summer 2007.
Water
Distribution Network:
New water connections to water
distribution networks will be
made with total cost of AED
15.65 million out of which AED
15 million in Sharjah, AED
650,000 in Khorfakkan and Kalba.
Other
water projects:
Construction of a new building
for the Directorate of water is
under progress.
A
new lab for Water Distribution
Department in Sharjah with total
cost of AED 0.5 million.
Zulal Water Factory:
Work is in progress to construct
of new factory, near Hamada
Water Station, with total cost
of AED 15 million. The new
factory will mainly depend on
raw from underground springs.
Zulal factory will shift to its
new location in 2007.
A
new g gallon line of 2000
bottles/hours with AED 4.5
million cost will be
commissioned by the end of 2006.
A
new R.O plant of 0.5 million
gallons per day capacity and 3
stainless steel tanks, with AED
0.5 million will be provided at
the new location.
Control Center:
Projects of AED 30 million will
be executed to link all SEWA
station within 2007.
Top
|