The allocation for the new
projects in 2008 budget which
amounts to AED 2,873 million,
will cover the following
projects:
- AED 665.7
million for Hamriyah Generation
& Desalination Expansion project
as follows: AED 349.8 for Phase
1 of installation and
commissioning of 5 combined
cycle gas turbines including the
civil works, AED 160 million for
Phase 1 of R.O units, AED 138.5
million for installation and
commissioning 4 desalination
units of 10 mgpd each, AED 17.4
million for construction of fuel
tanks, off loading terminal and
220 &132 KV switchgear
- AED 763.3
million for power distribution &
transmission projects in Sharjah
as follows: AED 120.2 million
for expansion of distribution
network in Sharjah areas. AED
156 million for construction of
12 X 33 KV substations, AED 30
million for lighting street
projects, AED 150 million for
construction of 3 X 132 KV
substations in Moweleh, Abu
Shaghara and Nasseriyah, AED
31.75 million for 132 KV
Substation Expansions of
Industrial areas 7 & 17 and
Nasseriyah, AED 104 million for
transmission projects out of
which AED 50 million for Wasit
132/220 KV Substation and AED 54
million for additions to Wasit
132 KV Substation, AED 113
million for construction of 132
& 220 KV cables in different
areas of Sharjah city, AED 44.4
million for various distribution
and transmission projects in
Sharjah city.
- AED 65 million
for natural gas projects out of
which AED 30 million for new gas
connections at newly developed
commercial and residential areas
in Sharjah and AED 35 million
for construction of piped
natural gas network in
Khorfakkan & Kalba.
- AED 254
million for water distribution
projects as follows:AED 30
million for Hamdah ń Badei 800
mm water main, AED 35 million
for Phase one of Hamriyah ń
Saja’a 1200 mm water main,
Saja’a Halwan 1200 mm water main
and Layyah ńMamzar 800 pipeline,
AED 40 million for phase 1 of
new storage tanks in Saja’a and
Falaj, AED 51 million for phase
1 of new pumping stations n
Saja’a, Hamda and Badie, AED 60
million for water distribution
network at King Abdul Aziz Road,
Layyah ń Nahda pipe line and
phase 1 of water distribution
system reinforcement, AED 37.5
million for water new AED
million for network developments
in areas of Rahmania and Suyouh
and AED 1 million for water
distribution system in Eastern
Zone.
- AED 174.25
million for electricity projects
in Khorfakkan as follows: AED
68.5 million for new F6 gas
turbine including civil work,
AED 91.25 million for
construction of 132 KV S/S, AED
14.5 million for construction of
33 KV S/S and other distribution
expansions.
- AED 117.4
million for electricity projects
in Kalba as follows: AED 11.3
million for construction of 132
KV S/S, AED 6.1 million for
various distribution expansion
projects.
- AED 34 million
for different projects at the
Head Office (AED 8 million) and
Layyah Generation & Desalination
Station (AED 26 million) The
budget also includes an
allocation of AED 799 million to
complete projects of 2007 all of
which aimed at fulfilling
requirements of nationals and
expatriates in the country.
|